Skerries Educate Together National School, Skerries, Co. Dublin.
Project Overview

Skerries Educate Together National School, Skerries, Co. Dublin.

Education

The project consisted of the design & build extension to existing primary school consisted of 10 no. new classrooms, 2 no. Specialist Teaching Rooms, General Purpose Hall and associated ancillary works. The design and build team planned a fast-track on-site construction duration of 26 weeks.  With an area of 2050 sq. m and 10 no. classrooms, this was awarded to ABM by the Department of Education Rapid Build Programme 2012.

Download Fact Sheet
  • Client

    Department of Education

  • Location

    Skerries, Co. Dublin

    Stage

    Completed June 2013

  • Client

    Department of Education

  • Status

    Completed June 2013

Project Details:

In 2012, the Department of Education prioritised funding to facilitate the construction of schools in rapidly developing areas such as Skerries, Co. Dublin.  Skerries Educate Together was an existing 2 storey school built circa and the programme was tendered on a design and build basis for the new 10 classroom extension with GP hall. It was intended that the school would be operational by the start of the school term in September 2013/14. The Actual commencement date was 10th December and was completed within a 26-week programme.

The project consisted of the construction of a 2 storey extension to existing primary school including link corridors comprising of 10 no. Classrooms, 2 no. support teaching specialist rooms, General Purpose Hall and ancillary accommodation with a total floor area of c. 2050 sq. m.  The site works to the school grounds involved of the provision of gardens & landscaping and boundary treatments.

  • Contractors Representative
  • Design and Construction Team Leader
  • To manage the design team members in the development and co-ordination of rapid build construction techniques and to ensure that the relevant information was available to achieve both the rapid start on site date and to adhere to the fast track programme
  • Sanctioning of all design decisions to ensure these were solutions which could achieve the rapid build programme
  • Ensuring that the design development adhered to the procurement and manufacture schedules, in particular the off-site production programme for the Kingspan panellised system used
  • Responsibility for all on-site construction activities
  • Responsibility for the management and co-ordination of health and safety matters on-site in our role as PSCS
  • Responsibility for the delivery of the project to a tight schedule including the commissioning and compliance with Schedule A of the DoE requirements for handover