Powerstown Education Campus, Dublin 15.
Project Overview

Powerstown Education Campus, Dublin 15.

Education

The project consisted of the design and build of two new 16 classroom schools on an existing school campus. The Educate Together National School building was completed in time for both the Gaelscoil and ETNS to move in at the start of the 2016 /17 academic year.                 

This project was led on a Design and Build (D&B) basis as part of the Department of Education Rapid Build Schools delivery programme 2015 – 2017. ABM’s role in the project was as Main Contractor and Project Supervisor for the Construction Stage (PSCS).

 

 

Download Fact Sheet
  • Client

    Department of Education

  • Location

    Powerstown, Dublin 15.

    Stage

    Completed April 2017

  • Client

    Department of Education

  • Status

    Completed April 2017

Project Description:

The two schools each consisted of 16 classrooms. In addition the ETNS had 2 class base Special Needs Units. Both schools contained other resource and teaching rooms, administration and circulation space. Site works consisted of 2 ball courts, junior play areas, disabled set down and parking, soft and hard landscaping, bin stores, bike sheds and car parking. Upgrading of the existing school entrances, external fencing and new public footpaths to the front of the site.

The project consisted of the strategically phased demolition of 2 no. existing primary schools and the construction of 2 no. new 16 classroom Primary Schools. The works comprise a number of construction/demolition phases.

Phase 1 comprised of the construction of 1 no. Primary School consisting of 16 Classrooms, 2 classroom Special Needs Unit, support teaching spaces and ancillary accommodation with a total floor area of c. 3087 m².

Phase 2 comprised of the demolition of the existing Gaelscoil an Chuilinn, a 6 Classroom Temporary Structure.

Phase 3 comprised of the construction of 1 no. Primary School, consisting of 16 Classrooms, support teaching spaces and ancillary accommodation with a total floor area of c. 2680 m².

Phase 4 comprised of the demolition of the existing Powerstown ETNS and the completion of site works to the grounds, including access roads, car park, drop off areas, play areas and landscaping.

Phase 5 comprised of alterations to existing car parks, set-down and construction of additional parking spaces on site.

Works were completed in 80 weeks.