Project Details:
The contract was awarded and works early July 2021 on site. The project was programmed to be completed in 88 weeks. Pelletstown ETNS was built using a Precast Concrete frame. The project was split into three phases. Phase 1 included a two story 8 classroom teaching building with roof top play area a GP hall and link corridor joining GP Hall to the teaching block. Phase 2 was the remainder of the main teaching building a 3 story, 8 classrooms with 2 classroom SNU on the ground floor. Phase 3 consisted of the completion of the external areas including ball court, bicycle parking, car parking etc.